Process Control of Surfacing Repair Quality for Roller Press Squeezing Rolls

Literature Overview

This paper, authored by Wang Zizhou from Jurong Taini Cement Co., Ltd., was published in New Century Cement Herald in 2011 (Vol. 17, No. 6, pp. 40–43). The study focuses on the process control of surfacing repair quality for the squeezing rolls of roller presses used in cement production. The paper emphasizes three key quality control aspects: proper wire selection, thorough understanding of the base material condition, and strict adherence to the welding process design. The practical results from the RP-Z170/180 roller press at Jurong Taini Cement confirm the importance of systematic quality control.

Technical Background

Roller presses are used in cement production to crush clinker and other materials. The squeezing rolls are subjected to extreme operating conditions:

The surfacing repair of these rolls is a critical maintenance activity that directly impacts production efficiency and cost.

Quality Control Process Framework

The paper outlines a three-pillar quality control framework:

Pillar 1: Wire Selection

The selection of the surfacing wire is the first and most critical decision. The wire must be chosen based on:

Common wire types for roller press surfacing include:

Wire Type Composition Application
High-carbon steel wire C > 2%, Cr, Mo Abrasive wear; moderate temperature
Nickel-based wire Ni-Cr-Mo-C High temperature; thermal fatigue
Tungsten carbide-filled wire Ni or Co matrix with WC Severe abrasive wear
Ceramic-filled wire Ni or Co matrix with B₄C, SiC Extreme abrasive wear

Pillar 2: Base Material Condition Assessment

Before surfacing, the base material must be thoroughly assessed:

Pillar 3: Welding Process Execution

The welding process must be executed according to the designed parameters:

Process Parameters for RP-Z170/180 Roller Press

The RP-Z170/180 roller press at Jurong Taini Cement uses the following surfacing parameters:

Parameter Value Notes
Welding process FCAW Flux-cored wire arc welding
Wire type High-carbon or Ni-based Selected based on wear mechanism
Wire diameter 1.6 mm Standard for FCAW
Welding current 300–400 A Adjusted for wire type
Arc voltage 30–38 V Maintained for stable arc
Travel speed 150–300 mm/min Controlled for layer thickness
Shielding gas CO₂ or Ar/CO₂ For flux-cored wire
Preheat temperature 300 °C For high-carbon base material
Interpass temperature ≤ 350 °C To prevent cracking
Number of layers 2–3 Total thickness 4–6 mm

Defect Analysis and Countermeasures

Defect Cause Countermeasure
Cracking High cooling rate; high carbon base Increase preheat; use Ni-based wire
Porosity Inadequate gas shielding; wire contamination Ensure clean wire; use proper shielding gas
Excessive dilution Too high current; too fast travel speed Reduce current; slow travel speed
Poor adhesion Inadequate surface preparation; contamination Grind to bare metal; clean thoroughly
Distortion Thermal input too high; constrained geometry Control preheat; use back-up plate

Quality Control Inspection Plan

A comprehensive inspection plan should include:

  1. Pre-weld inspection: Visual inspection, MT/UT for defects, hardness mapping, chemical analysis.
  2. In-process inspection: Monitor welding parameters, check interpass temperature, inspect each layer for defects.
  3. Post-weld inspection: Visual inspection, PT for surface cracks, hardness testing, dimensional measurement.
  4. Final acceptance: Verify overlay thickness, hardness, and surface finish according to specifications.

Study Reflections

This paper, while focused on a specific application (cement roller press), presents a universal quality control framework that can be applied to any surfacing repair operation. The three pillars—wire selection, base material assessment, and process execution—are fundamental to any surfacing project. The emphasis on systematic quality control is particularly valuable in industrial settings where maintenance is often performed under time pressure and with limited resources. The practical results from the Jurong Taini Cement case study confirm that investing in quality control pays dividends in terms of service life and cost savings.