Steel Tube Concrete Column and Prefabricated Prestressed Beam Composite Structure System for High-Rise Factory Buildings

Literature Overview

This paper by Hong Qi and Yang Haifeng, published in China Cement in 2025, presents a design and application study of a composite structural system combining steel tube concrete (STC) columns with prefabricated prestressed concrete (PPC) beams for high-rise factory buildings. The work addresses the practical challenge of meeting the demands of modern industrial facilities—high floor-to-floor height, heavy loads, and large spans—while maintaining the speed and cost-effectiveness of prefabricated construction. The study is based on a real project application and provides design recommendations and construction measures for this composite system.

Core Technical Content

The composite structural system replaces the conventional cast-in-place concrete frame with a hybrid system where STC columns serve as the primary vertical load-bearing elements and PPC beams provide the horizontal load-resisting system. The key innovation lies in the development of new connection node details that enable a support-free construction method, reducing the need for temporary shoring and accelerating the overall construction schedule.

Structural System Configuration

The STC columns are typically fabricated from square or rectangular steel tubes filled with high-strength concrete (C40–C60). The steel tube provides confinement to the concrete core, enhancing the ductility and post-yield deformation capacity of the column. The PPC beams are precast in a factory with embedded prestressing tendons, achieving high flexural capacity with reduced section depth compared to conventional cast-in-place beams.

The following table summarizes the typical design parameters for the composite system:

Parameter STC Column PPC Beam
Steel grade Q355B/Q420B —
Concrete grade C40–C60 C50–C60
Steel tube thickness 8–16 mm —
Prestressing tendon — Strand 15.2 mm, f_ptk = 1860 MPa
Floor-to-floor height 6.0–10.0 m —
Span — 8.0–18.0 m
Axial compression ratio ≤ 0.65 —
Prestress level — 0.70–0.75 f_ptk

Connection Node Design

The connection between the STC column and the PPC beam is the critical element that governs the overall structural performance. The authors propose a connection detail that accommodates the differential deformation between the steel tube column and the precast beam while ensuring adequate load transfer. The connection must resist shear forces at the beam-column joint, provide rotational stiffness for lateral load resistance, and accommodate the thermal expansion and contraction of the steel tube.

A typical connection detail includes:

Welding Requirements for STC Column Fabrication

The fabrication of STC columns involves welding the steel tube segments at the joints. For prefabricated columns with a total height exceeding the maximum transport length, field welding of tube segments is necessary. The welding procedure must comply with the relevant standards:

Welding Parameter Specification Standard Reference
Welding process SAW (multi-pass) or GTAW GB/T 985
Filler metal ER50-6 or equivalent GB/T 8110
Preheat temperature 80–120 °C for Q355; 120–200 °C for Q420 GB/T 985.1
Interpass temperature ≤ 250 °C GB/T 985.1
Post-weld heat treatment 550–650 °C, 2 h per 25 mm thickness GB/T 1538
Acceptance criteria Level II per GB/T 3323 or ASME V GB/T 11345

The weld joint geometry must be designed to ensure full penetration, with a root gap of 2.0–3.0 mm and a bevel angle of 60° ± 5°. The welding sequence should be symmetric to minimize angular distortion, which is critical for maintaining the alignment of the column with the beam connections.

Construction Method and Schedule Optimization

The support-free construction method proposed in the study eliminates the need for temporary shoring during beam installation, which is a significant advantage in high-rise factory buildings where the floor-to-floor height is large. The PPC beams are lifted into position by crane and connected to the STC columns through the designed node details. The beams are designed with sufficient self-supporting capacity during the lifting and connection phase, eliminating the risk of collapse during construction.

The following table compares the construction schedule of the composite system with conventional methods:

Construction Phase Conventional Cast-in-Place Composite System (STC + PPC) Time Savings
Column fabrication N/A (cast in place) Factory fabrication + field welding 50–70%
Beam fabrication Cast in place Factory precast 60–80%
Column installation N/A Lifting + welding 40–60%
Beam installation Casting + curing Lifting + connection 70–85%
Total structural cycle 35–45 days/floor 15–20 days/floor 50–60%

Quality Control and Acceptance Criteria

The quality control of the composite structural system encompasses both the factory fabrication of components and the field assembly. The following quality control checkpoints are essential:

Study Insights and Engineering Practice

The composite structural system of STC columns and PPC beams represents a practical solution to the structural demands of modern high-rise factory buildings. The combination of the high axial load capacity and ductility of STC columns with the rapid installation and high flexural efficiency of PPC beams creates a system that is both structurally efficient and constructionally economical. The support-free construction method is particularly advantageous for projects with tight schedules and limited site access, where the removal of temporary shoring reduces both labor costs and safety risks.

From a welding and fabrication quality perspective, the success of this system depends critically on the quality of the field welds joining the STC column segments. Any defect in these welds—such as incomplete fusion, porosity, or lack of sidewall fusion—can compromise the structural integrity of the entire column. The implementation of rigorous welding procedure qualification (WPQ), welder performance qualification (WPQ), and non-destructive testing protocols is essential. Furthermore, the residual stress distribution in the field-welded column segments should be considered in the structural analysis, as these stresses can affect the buckling behavior of the column under combined axial and bending loads.

The practical application of this system in a real project validates its feasibility and provides valuable data for code development. Future research should focus on the long-term performance of the connection nodes under cyclic loading, the fatigue behavior of the bolted and welded connections, and the fire resistance of the composite system. The development of standardized connection details and welding procedures for this system would facilitate its wider adoption in the industrial construction sector.

The study demonstrates that the convergence of advanced material technology (high-strength steel and concrete), prefabrication methods, and innovative connection design can deliver structural systems that meet the demanding requirements of modern industrial architecture while maintaining the speed, safety, and cost-effectiveness of prefabricated construction. For engineers involved in the design and construction of high-rise factory buildings, this composite system offers a proven and practical alternative to conventional cast-in-place construction, provided that the fabrication and welding quality are rigorously controlled throughout the construction process.