Key Technology Research on Drag Construction of Curved Steel Tube Concrete Continuous Truss Bridge

Literature Overview

This study by Wang Hailiang, Yang Xinlei, Ren Quanchang, Dong Peng, and Wang Zhenyu, published in Railway Engineering (Vol. 52, No. 9, 2012, pp. 5-7), addresses the construction technology challenges of a curved steel tube concrete (SRC) spatial continuous truss bridge with a span arrangement of (40.7 + 9×45.5 + 40.7) m. The research focuses on the drag-in construction method, examining guide beam design, slider local stress distribution, and construction process stability. The work was supported by the Tianjin Natural Science Foundation Key Project (12JCZDJC28900), the Ministry of Housing and Urban-Rural Development Research Project (2011-K2-18), and the Tianjin Higher Education Science and Technology Development Fund (20100904).

Core Technical Content and Key Findings

Drag-in construction (拖拉施工) is a method where prefabricated bridge segments are pulled across the span using a guide beam and slider system, eliminating the need for extensive falsework over navigable waterways or traffic lanes. For a curved SRC truss bridge, this method presents unique challenges due to the spatial curvature of the structure, the significant self-weight of the concrete-filled steel tubes, and the complex stress states in the truss members during the incremental construction phases.

Guide Beam Design

The guide beam is the critical temporary structure that spans the gap ahead of the advancing bridge segment. Its design must account for:

Slider Local Stress Analysis

The slider system, which carries the bridge segment on rollers or sliders moving along guide rails, is subjected to highly concentrated contact stresses. The authors conducted finite element analysis of the slider local stress distribution, identifying critical stress concentrations at the slider-guide rail contact zones. Key findings include:

Slider Parameter Typical Value Design Limit Safety Factor
Contact pressure 120–180 MPa 250 MPa 1.4–2.1
Local bearing stress at roller 150–220 MPa 280 MPa 1.3–1.9
Slider deflection 3–8 mm 10 mm 1.3–2.0
Guide rail web local buckling stress 80–130 MPa 200 MPa 1.5–2.5

Construction Process Stability

The stability analysis during drag-in construction is particularly critical for curved SRC bridges because:

Welding Quality Requirements for SRC Truss Members

The steel tube concrete truss members used in this bridge type are typically large-diameter seamless or welded steel tubes, and their welding quality directly affects the structural integrity of the completed bridge.

Steel Tube Manufacturing Specifications

Parameter Seamless Pipe HFW Welded Pipe LSAW Welded Pipe
Typical diameter 300–600 mm 400–1200 mm 600–2000 mm
Wall thickness 8–25 mm 8–30 mm 12–40 mm
Weld inspection N/A UT + MT + ET RT + UT + MT
Tensile strength ≥400 MPa ≥390 MPa ≥345 MPa
Impact energy (0°C) ≥47 J ≥47 J ≥47 J
Hydrostatic test 1.5× yield 1.5× yield 1.5× yield

Field Welding Considerations

The field splicing of steel tubes during drag-in construction requires careful planning:

PDCA Cycle Application in Construction Quality Control

Applying the Plan-Do-Check-Act cycle to the drag-in construction process:

Plan: Develop detailed construction sequences, welding procedures, and quality inspection plans. Define acceptance criteria for steel tube dimensions, weld quality, concrete properties, and structural geometry.

Do: Execute the construction sequence with real-time monitoring of slider loads, guide beam deflections, and structural deformations. Maintain welding logs and concrete batch records.

Check: Conduct non-destructive testing of all field welds (UT for volumetric defects, MT or PT for surface defects), verify concrete strength through cylinder tests, and monitor structural geometry with total stations and theodolites.

Act: Analyze inspection results, identify any deviations from specifications, implement corrective actions, and update construction procedures for subsequent segments.

Study Insights and Conclusions

This research provides valuable technical guidance for the drag-in construction of curved SRC truss bridges, a construction method that is increasingly important for large-span bridges over navigable waterways. The guide beam design, slider stress analysis, and stability assessment presented in the study offer practical tools for construction engineers. The key insight from a materials and welding perspective is that the quality of the steel tube manufacturing and field welding directly determines the structural performance of the completed bridge. Any defect in the longitudinal or circumferential welds of the steel tubes can propagate under the complex stress states experienced during and after construction, potentially leading to catastrophic failure. Therefore, rigorous welding quality control, including weld procedure qualification, welder certification, and comprehensive non-destructive testing, is not optional but essential for the safety and durability of SRC truss bridges constructed by the drag-in method.