Analysis of Mixed Construction Methods for Steel Tube Concrete Arch Bridges

Literature Overview

The paper by Tang Jishun, Hu Tao, Chen Yuanjiu, and Wu Xuwei from Southwest Jiaotong University, published in Sichuan Building Science (2017, Vol. 43, No. 6, pp. 122-126), addresses a practical construction challenge in steel tube concrete (CSTC) arch bridge erection. The study proposes a hybrid construction method that combines formwork-supported construction for the arch foot segments with cable-sling (hanging) construction for subsequent segments. This approach was developed for a specific through-arch CSTC bridge with complex site constraints, and the feasibility was verified through Midas/Civil finite element analysis.

Construction Methodology Comparison

The study compares two construction approaches:

Construction Method Applicable Segments Equipment Required Key Advantage Key Limitation
Formwork-supported (scaffolding) Arch foot segments Scaffolding, formwork, concrete pump High accuracy, stable working platform Requires extensive ground support, site-dependent
Cable-sling (hanging) Main arch segments Cable-sling system, lifting equipment Suitable for large spans, less ground interference Line shape control is more challenging
Mixed method (proposed) Combined approach Both systems Best of both methods Complex transition between methods

Technical Analysis of the Mixed Method

Design Rationale

The mixed construction method was proposed based on the following considerations:

Finite Element Analysis Results

The Midas/Civil analysis revealed the following key findings:

  1. Internal force distribution: The final internal force distribution in the completed arch is approximately the same regardless of whether the pure cable-sling method or the mixed method is used. This indicates that the construction method has limited influence on the final structural capacity.
  2. Line shape accuracy: The mixed construction method produces a final arch line shape that more closely matches the design line shape compared to the pure cable-sling method. This is because the formwork-supported arch foot segments provide a more accurate foundation for the subsequent cable-sling segments.
  3. Construction feasibility: The mixed method is technically feasible for bridges with suitable site conditions and high line shape accuracy requirements.

Key Technical Parameters

Parameter Design Consideration Typical Value
Arch foot segment length Depends on scaffolding span capability 10-20 m
Cable-sling segment length Determined by lifting capacity and stability 8-15 m
Cable-sling angle Affects vertical and horizontal force distribution 30-60 degrees
Line shape tolerance Depends on design requirements ±10-20 mm
Concrete strength at cable-sling removal Must develop sufficient strength ≥70% of design strength

Engineering Practice Considerations

Quality Control Points

For the successful implementation of the mixed construction method, the following quality control measures are essential:

Risk Assessment (FMEA Approach)

Potential Failure Cause Effect Prevention
Scaffolding collapse Overloading or inadequate design Safety hazard, construction delay Structural analysis, load testing, inspection
Line shape deviation Inaccurate cable-sling positioning Aesthetic and structural issues Survey monitoring, real-time adjustment
Transition joint cracking Differential settlement or shrinkage Structural integrity concern Proper reinforcement, controlled concrete placement
Cable-sling failure Overloading or fatigue Safety hazard Load rating, inspection, redundancy

Study Insights and Conclusions

This research provides practical guidance for the construction of CSTC arch bridges in challenging site conditions. The key insight is that the mixed construction method offers a balanced solution that combines the accuracy of formwork-supported construction with the efficiency of cable-sling methods. The finding that the final internal force distribution is largely independent of the construction method is reassuring from a structural safety perspective, as it means that the construction method can be selected based on practical considerations without compromising the final structural performance. However, the superior line shape accuracy achieved with the mixed method is a significant advantage for bridges with stringent geometric requirements, such as those carrying railway or high-speed road traffic. For engineers planning CSTC arch bridge construction, this study demonstrates that the construction method selection should be driven by site conditions, line shape requirements, and construction resources, rather than structural performance concerns alone. The finite element analysis approach used in this study, while not capturing all construction details, provides a reliable framework for evaluating construction method alternatives. Future research could extend this analysis to include time-dependent effects such as concrete shrinkage and creep, which may influence the long-term line shape and internal force distribution of the completed bridge.