ZHUOJIN-LOGOZhuojin Pipe Fitting Co., Ltd
Zhuojin Pipe Fitting Co., Ltd
STEEL PIPE · FITTING · WELDING TECHNICAL STUDY

Steel Pipe Jacking in Yangzhou Water Plant Turbid Water Pipeline Project

Literature Overview

This paper published in China Water Affairs (2014, Vol. 30, No. 10, pp. 100–102) by Zheng Quanxing, Yue Bing, and Xu Yingwu from Yangzhou Water Company and Shanghai Foundation Engineering Group, documents the practical application of pipe jacking technology for a DN2000 turbid water pipeline crossing the Beijing-Hangzhou Grand Canal at Yangzhou's first water treatment plant. The project involved substantial jacking distances, challenging geological conditions, and complex surrounding environments, making it an instructive case study for engineers involved in large-diameter pipeline jacking operations.

Core Technical Content

Project Background and Challenges

The DN2000 turbid water pipeline required to cross the Beijing-Hangzhou Grand Canal, one of China's most important waterways. The project faced several distinctive challenges:

Key Technical Measures

The paper details several critical technical measures that ensured successful project execution:

Technical Measure Purpose Implementation Detail
Intermediate jacking stations Reduce cumulative friction force Strategically placed along the jacking route to break the jacking force into manageable segments
Tool head breakout Ensure controlled and safe exit from shaft Careful ground improvement and gradual breakout to prevent ground collapse
Pipe welding Achieve structural integrity of the jacked pipeline Field welding of pipe segments with strict quality control
Grouting and friction reduction Minimize jacking resistance Synchronous grouting behind the tool head to reduce skin friction
Tool head entry into receiving shaft Controlled and damage-free entry Precise alignment and gradual entry to prevent pipe damage or misalignment

Intermediate Jacking Station Design

The most technically significant aspect of this project was the design and implementation of intermediate jacking stations. For a DN2000 pipe, the cumulative friction force over a long jacking distance can exceed the capacity of a single jacking station. The intermediate stations effectively divide the jacking force into segments, with each station bearing only the friction force for the pipe length between it and the next station.

Key design considerations for intermediate jacking stations include:

Pipe Welding in Jacking Operations

The field welding of DN2000 pipe segments is a critical quality control point. The paper emphasizes that the welding must achieve:

For large-diameter pipes, the welding procedure typically involves:

  1. Pre-fit and alignment of pipe ends with precise gap control.
  2. Root pass welding using GTAW (TIG) for full penetration.
  3. Fill passes using SMAW or FCAW.
  4. Cap pass welding with proper profile finishing.
  5. Non-destructive testing (RT or UT) of critical welds.

Engineering Practice Implications

This case study provides valuable lessons for engineers planning large-diameter pipe jacking projects:

Key Questions and Reflections

One question that arises from this case study is the long-term performance of the welded joints under sustained compressive loading. While the initial welding quality may be satisfactory, the cyclic loading during jacking and the sustained service loads could potentially affect the weld integrity over time. Additionally, the paper's emphasis on construction measures rather than detailed material or welding procedure specifications suggests that the project relied heavily on experienced workmanship, which raises questions about reproducibility and standardization.

Summary

The Yangzhou water plant pipe jacking project demonstrates the successful application of large-diameter pipe jacking technology under challenging conditions, with intermediate jacking stations, controlled breakout and entry procedures, field pipe welding, and grouting-based friction reduction as the key technical pillars. The case study underscores that large-diameter jacking operations require careful integration of geotechnical analysis, structural design, welding quality control, and construction management to achieve successful outcomes in complex environments.